The Kitchen Remodel Checklist
Every decision, in the order it actually has to be made — from first measurement to final walkthrough. Free to download, no email required.
Free, No Email Required
Print it, tick it off, take it to your contractor.
No form. No follow-up calls.
Most Kitchen Remodels Don’t Fail on Budget. They Fail on Sequence.
The expensive mistakes in a kitchen remodel are almost never about picking the wrong quartz. They are about doing things in the wrong order: templating countertops before the cabinets are shimmed level, finalising electrical rough-in before the layout is genuinely locked, ordering cabinets before anyone has confirmed the appliances fit.
Each of those is recoverable. Each costs weeks and thousands of dollars to recover from. And each is entirely avoidable by making the decisions in the order below.
This checklist is organised by phase rather than by category, because that is how a remodel actually unfolds. Work through it top to bottom. The printable version is free and needs no email address — take it to whoever ends up doing your project.
Before You Contact Anyone
Two to four weeks. Do this and every conversation afterwards is shorter and more useful.
Write down what’s actually wrong
Not “it’s dated.” Specifically: not enough counter space left of the sink, no landing zone by the oven, the fridge door blocks the walkway. Symptoms, not solutions — a good designer will solve them in ways you would not have thought of.
Track how you really use it
For one week, note where you prep, where groceries land, who else is in the room while you cook. Kitchens fail on traffic patterns more often than on square footage.
Set a real number, then a ceiling
Decide what you want to spend and the absolute maximum. The gap between them is your contingency — and you want 10–15% of the total sitting in it before you start.
Measure the room yourself
Wall lengths, ceiling height, window and door positions, and where the sink, range and fridge currently sit. Rough is fine. It makes early quotes far more accurate.
Photograph everything
Every wall, inside every cabinet, the panel, under the sink. You will reference these constantly and it costs five minutes.
Decide if you’re staying
Living through it saves money and costs sanity. If you are staying, plan the temporary kitchen now — microwave, kettle, fridge access, somewhere to wash up.
Design and Scope
This is the phase where money is genuinely saved or quietly wasted, and it is the one people rush.
Lock the layout before anything else
Every downstream decision depends on it. Moving the sink or range after cabinets are ordered means new cabinets. The single biggest cost saver in any remodel is keeping plumbing and gas where they are — if the existing layout works, resist changing it for the sake of it.
Confirm appliances before cabinets
Cabinet openings are built to appliance dimensions, not the other way round. Pick the actual models — including the counter-depth versus standard-depth fridge decision, which changes the whole run — and give the specs to whoever is drawing the cabinets.
Get a written line-item quote
Not a lump sum. You want cabinets, counters, flooring, electrical, plumbing, demolition, and disposal broken out. “Allowances” are where budgets go to die — an allowance is a guess with your name on it, and it always resolves upward.
Ask what’s excluded
This one question surfaces more surprises than any other. Painting? Appliance installation? Disposal fees? Permit costs? Backsplash? Under-cabinet lighting? Get the answer in writing.
Contractor Checks You Shouldn’t Skip
| Check | Why It Matters |
|---|---|
| Licence and insurance, verified — not just claimed | Ask for the certificate. An uninsured injury on your property can become your liability. |
| Registered in your municipality | Some towns require contractor registration before any permit is issued. An unregistered contractor stalls the project before demolition day. |
| Who pulls the permit | If the answer is “you do,” ask why. Contractors pulling their own permits keeps responsibility where it belongs. |
| Three recent references, actually called | Ask specifically: did the schedule hold, and how were change orders handled? |
| Payment schedule tied to milestones | Never a large deposit up front. Payments should track completed phases. |
| Change-order process in writing | Agree how changes get priced and approved before you need one. You will need one. |
| Named point of contact | One person who answers the phone when something needs deciding at 8am. |
Permits — and Why They’re Not Optional
Cabinet and countertop replacement in the existing footprint usually needs no permit. The moment you move plumbing, add or relocate electrical circuits, touch gas, or remove a wall, you are in permit territory.
Skipping it is a false economy that surfaces years later. Unpermitted work turns up during a home sale, and the buyer’s lender may require it to be opened up, inspected and corrected — on your schedule and at your cost, long after the contractor has gone.
The part that catches people out: which authority issues your permit depends on your address, and the answer is often not the obvious one. It varies between a city, a township, and a county even within a single metro area. Confirm it before anyone submits anything — applying to the wrong desk means starting over.
In the Toledo area specifically, that varies by community. Our Sylvania, Maumee, Whitehouse and Perrysburg pages each set out the exact process for that community.
The Build, In Order
This sequence isn’t preference. Reorder it and things have to be undone.
| # | Stage | The Thing People Get Wrong |
|---|---|---|
| 1 | Demolition & discovery | Budget time for what the walls hide. This is when surprises surface, not later. |
| 2 | Rough-in: electrical, plumbing, HVAC | Layout must be final. Every change after this point is expensive. |
| 3 | Rough-in inspection | Book it in advance. Miss the window and drywall stalls, and everything after drywall stalls with it. |
| 4 | Drywall, patching, priming | Do not close walls before the inspection passes. Ever. |
| 5 | Flooring | Usually goes under the cabinets. Costs a little more material, protects you if the layout ever changes. |
| 6 | Cabinet installation | Boxes get shimmed and scribed level. Old houses are not square, and countertops reveal it. |
| 7 | Countertop templating | Only after cabinets are set. Templating from drawings produces gaps at the wall. |
| 8 | Countertop installation | Typically 7–14 days after templating. Plan meals around it. |
| 9 | Backsplash | After counters, so the tile sits on a real surface rather than a predicted one. |
| 10 | Trim-out: lighting, fixtures, hardware | The fast, satisfying part — but final inspection still has to follow. |
| 11 | Final inspection & walkthrough | Punch-list every drawer, hinge, seam and switch before the final payment. |
Before You Pay the Final Invoice
The walkthrough is the last moment your leverage is worth anything. Take it seriously and take an hour over it.
Open and close every door and drawer — all of them. Check soft-close actually engages. Run water in the sink and look underneath for drips while it runs. Test every outlet, including the GFCI trip and reset. Turn on every light and every switch. Look along the countertop seams from a low angle, where flaws show. Check cabinet doors line up with each other, not just with their own frames. Confirm the appliances are level and secured. Ask for warranty documents, paint colour codes, and any leftover tile.
Write the punch list down and agree a date for it. A verbal list is not a list.
Checklist FAQ
How far ahead should I start planning?
Cabinet lead times set the pace — typically 3–8 weeks after ordering. Add design and quoting before that. Two to three months from first conversation to demolition is normal and worth allowing for.
What’s the single biggest cost driver?
Cabinets, then countertops — together usually 40–50% of the budget. The biggest hidden multiplier is moving plumbing or gas, which is why layout changes deserve real scrutiny.
Do I really need a 10-15% contingency?
Yes, and treat it as spent from day one. Older homes hide knob-and-tube remnants, galvanized supply lines, and joists notched by someone with a confident saw. Unused contingency means finishing under budget; missing contingency means stalling mid-project.
Can I do some of the work myself to save money?
Demolition and painting are the realistic candidates. Electrical, plumbing and gas are not — they need permits and licensed work, and a failed inspection costs more than the labour you saved.
Is the PDF really free?
Yes. No email, no form, no follow-up call. Download it here.